HOHANK INTERNATIONAL GEN LATAM

Mine drainage pump backup power supply

Mine drainage pump backup power supply

For open-pit mines, underground mines, tailings pumps, water treatment stations, rainy season drainage and safety loads, diesel generator sets, ATS, low-voltage power distribution and critical load backup power are configured.

Mine drainage pump backup power supply

Sewage pump backup power supply

Pumping and drainage are often safety-critical loads and need to be incorporated into protected loads rather than ordinary auxiliary equipment.

Scene background

Drainage, tailings and safety loads cannot be treated the same as ordinary production loads.

The electricity risks of open pits, underground working surfaces, tailings systems and water treatment stations are different from those of ordinary production equipment. Stopping the crushing line will affect production, and stopping the drainage pump may cause water accumulation, safety, environmental protection, and recovery difficulties.

In the early days, many sites connected pumping stations, lighting, campsites and production equipment to the same power supply. They could run normally. However, in the rainy season, power outages or voltage fluctuations, critical safety loads would be dragged down by ordinary loads.

Onsite issues

Once the water pump stops, the site will not produce less, but the risk will rise rapidly.

The biggest concern for the person in charge of mine operations is that the pump cannot automatically recover during a power outage, or the voltage is unstable when the pump is restarted. Water accumulation in open-pit mines, interruption of drainage at underground working surfaces, and shutdown of tailings pumps will all put the site into a passive treatment state.

On-site personnel may have to switch power supplies in the rain, check pump control cabinets, deploy temporary units, and also ensure lighting, communication and safety equipment at the same time. Electrical problems can quickly turn into safety and production organization issues.

Mine drainage pump backup power supply on-site problem scenario

The impact of not processing

Ignoring drainage and ensuring power will amplify downtime, equipment damage and recovery costs.

Once the pumping and drainage system is shut down for a long time, water accumulation may affect roads, pit bottom equipment, underground working surfaces and electrical cabinets. Restoration not only involves restarting the pump, but also dealing with silt, damp, cable and control system risks.

Loads such as tailings, water treatment, and ventilation may also create regulatory and site safety pressures if they lack backup power. This problem cannot be solved only by temporary repairs, but protected loads need to be defined in advance.

Recommended configuration

Treat pumping and drainage as a key load and configure dedicated backup power supply

Key pumps, pump control cabinets, necessary lighting, control signals and communications should be separately classified into the backup power supply range, and prioritized with ordinary loads such as crushing, maintenance workshops, and campsites. In the event of a power outage, which pumps will be protected first and which pumps will be started later must be clearly stated on the power distribution side.

Backup diesel engines, ATS, pump starting current review, rain-proof and moisture-proof power distribution, long-term fuel and key spare parts should be planned together. What the pumping station really needs is not a unit that can be temporarily connected, but a switching sequence that does not need to be debated again after a power outage.

Configuration confirmation steps

Delineate critical pumps and review startup, switchover, and long-term operation

In the first step, the pump groups are divided according to risk: pit drainage, underground working surface, tailings, water treatment and fire-fighting loads are looked at separately, and the pump power, starting method, control cabinet position, rainy season water volume and manual restart difficulty are recorded.

The second step is to review the backup unit capacity, ATS range and pump start sequence. Multiple pumps cannot be started at the same time by default, and pumping stations cannot compete with lighting, dormitory, and maintenance equipment for the same set of spare capacity.

The third step is to incorporate rainy season conditions into the design. The rain-proof and moisture-proof power distribution cabinets, fuel tank endurance, duty arrangements, spare contactors and sensor inventory must all be confirmed before the water level rises, instead of waiting to find after the pump is stopped.

Onsite income

During a power outage, first protect the water and control the load, so on-site recovery is more controllable.

When the mains power supply or the main power supply is abnormal, the key pumps can be switched to the backup power supply according to priority, and the capacity is given up to the ordinary load. The site no longer relies on manual wire pulling and temporary judgment in the rain to maintain drainage.

What the team received was a drainage and power guarantee list: the required pump set, backup power supply coverage, fuel life, on-duty actions, common spare parts locations and abnormal reporting sequence were all fixed in advance.

Check before quotation

Common signals on site

  • Open pits or underground operations have a high risk of water exposure
  • The pump must continue to operate during rainy seasons or power outages.
  • Difficulty in recovery after stopping the pump for a long time
  • Pump control system is in a humid or remote area

If you don’t plan ahead

  • A power outage can put drainage, tailings, water treatment or ventilation loads into a passive processing state
  • It is difficult to restart the pumping station, and water accumulation may affect roads, equipment and working surfaces
  • It is necessary to manually switch the power supply in the rain, which increases safety risks and recovery time.
  • Critical pumps and ordinary loads compete for the same set of spare capacity, and the protection priority is unclear
  • Lack of long-term fuel and spare parts plans, and recovery from shutdowns in rainy season is slower

Project confirmation points

  • Which pumps, control cabinets, lighting and communications are safety critical loads?
  • Pump power, starting method, number of simultaneous starts and restart difficulty
  • Rainy season water volume, continuous operation time and on-site duty requirements
  • ATS switching range, spare capacity and common load isolation method
  • Rain and moisture-proof conditions of pump station, fuel tank configuration and key spare parts inventory

Recommended configuration range

  • Configure dedicated backup generators for critical pumps
  • ATS and critical load prioritization
  • Review pump starting current
  • Planning fuel for long-term operations
  • Rainproof, moistureproof and key spare parts configuration

Engineer assistance

Contact the engineer first, and then determine the equipment and service scope together

Are drainage, tailings, water treatment or ventilation loads safe loads that cannot wait after a power outage?

Device and module scope

Backup diesel generator set, ATS automatic switching, rainproof power distribution, pump start review, long-term fuel and critical spare parts.

Engineers will help you sort out the information

  • Pumping station power, quantity and starting method
  • Rainy season operation time and drainage priority
  • Photos of existing control boxes, piping areas and wet environments
  • Allowed interruption time and backup time after power outage

Related equipment and services

Standby diesel generator setATS switchingRainproof low voltage power distributionFuel lifeKey spare parts package

Engineer contact

Contact the engineer first and let the engineer help you determine the configuration.

If the information is incomplete, you can contact us first. You only need to first explain the location of the mining area, on-site problems or general equipment conditions, and the engineer will work with you to sort out the load, site conditions and configuration range.

Scan the WhatsApp code to contact the engineer

Engineers will contact you soon to understand your questions and needs.

Scan the WhatsApp code to contact the engineer
or leave your contact information

Engineers will contact you soon to understand your questions and needs.

Contact engineer service