Temporary mine power plan

Temporary mine power plan

For new mines, expansions, camps, drilling, welding, temporary crushing and trial production, configure mobile or container gensets, temporary distribution, fuel and expansion interfaces.

Temporary mine power plan

How to turn temporary mine power into an expandable system

During new-mine construction, expansion and EPC work, temporary power cannot be improvised. Camps, roads, dewatering, lighting, maintenance points, drills, welders, pumps, construction lines and later trial-production loads must sit in one phased power plan so equipment can start when it reaches site.

Scene background

New mines and expansion projects often need power before the stable grid arrives

When mines shift from exploration to construction, and from old mine sites to new pit mouths, the first thing started on site is often not the complete production line, but roads, drainage, camps, lighting, maintenance points, drilling rigs, welding machines and construction equipment. These loads appear to be scattered, but they all affect the construction progress.

If construction power is treated only as a temporary patch, the site tends to borrow generator sets again, pull new cables, and revise distribution every time the project advances to another stage. It may look convenient early on, but by installation, commissioning, and trial production, the power-supply relationship becomes harder to clarify.

Site problem

Equipment arrives on site, but power, distribution, and cable paths are not ready

Mine owners, expansion leads, and EPC contractors worry most when equipment has arrived but hoisting, welding, pump stations, lighting, and temporary processing lines cannot run at the same time. Site crews can only shut off some loads temporarily or keep moving generator sets and cables back and forth.

This is not simply a missing generator set. It is a missing phased power plan. If construction, commissioning, trial production and later expansion are not reviewed together, temporary power becomes a site coordination cost.

Temporary power plan for mine construction on-site issue scenarios

Operational consequences if left unresolved

Improvised power at each stage slows construction, commissioning and trial production

Without reliable temporary power, civil works, dewatering, roads, camps and maintenance points compete for capacity. When welders, drills or pumps start, lighting, tools or temporary processing lines may have to give way, repeatedly interrupting construction.

The larger losses appear later. If temporary construction power leaves no interfaces for trial production or expansion, adding loads later means rewiring, adding cabinets, and moving generator-set positions, raising site cost and blurring responsibilities.

Recommended configuration

Make temporary power a phased system rather than improvising

Divide the construction period, installation and commissioning, trial production and subsequent expansion into several stages, and list the loads that must be protected first in each stage. Campsites, roads, drainage, lighting, maintenance points, pumping stations, drill rigs, welders and temporary treatment lines are prioritized.

Configuration usually requires mobile or containerized generator sets, temporary distribution cabinets, low-voltage output protection, cable route planning, daily fuel tanks, and refueling access. The focus is not on building large generating capacity at once, but on allowing the system to expand as the site progresses.

Configuration confirmation steps

Plan generator location, distribution, and refueling routes for each load stage

Map loads against the site layout and project milestones: which loads must run now, which start during installation and commissioning, and which only enter continuous operation during trial production.

Confirm generator placement, movement path, temporary distribution cabinet location, and cable routing early, so roads, lifting work, drainage ditches, fuel-truck access, and construction traffic do not conflict later.

Reserve paralleling control, distribution capacity, and cable interfaces for later expansion, so temporary power can carry the project from construction into trial production without rebuilding the system at every stage.

Expected operational benefit

There is electricity on site first, and there are clear plans for subsequent trial production and capacity expansion.

The goal is to keep camp, roads, dewatering, lighting, maintenance points and construction equipment running first. New equipment can connect by priority during commissioning, without reworking the full power relationship during trial production.

The mining team and EPC contractor receive more than a temporary genset. They get an executable site power plan: which loads to protect now, where the next expansion connects, and how tanks and cables move with construction.

Information to confirm before quotation

Common site signals

  • The power grid has not been stabilized in the early stage of the construction of the new mine, but roads, drainage, camps, lighting and maintenance points have to be started first
  • New equipment, construction lines, pumps, drills or welders need power before installation and commissioning.
  • At each site stage, crews add another temporary cable section and borrow another generator set, making the distribution relationship increasingly chaotic.
  • The temporary processing line or trial-production plan is scheduled, but construction-stage power has no reserved interface for later expansion.
  • Fuel-tank location, refueling route, cable routing, and equipment placement are not checked against the overall construction layout.

If this is not planned early

  • Lack of reliable power will slow down civil construction, equipment installation, commissioning and trial production
  • Drilling rigs, welding machines, pumping stations, lighting and maintenance points compete for power from each other, and only part of the load can be temporarily stopped on site.
  • Equipment may reach the site before generation capacity, distribution, or cable routes are ready for connection
  • Replenishing power, changing wiring, and borrowing equipment are required at each stage. The cost is high, and the division of responsibilities can easily be confused.
  • Temporary construction power did not account for trial production or expansion, so added loads later force the site to redesign the temporary power plan.

Project confirmation points

  • List the load in stages during the construction period, installation and commissioning, trial production and subsequent expansion.
  • Confirm priorities for campsites, roads, drainage, lighting, maintenance points, pumping stations, drill rigs, welders and temporary processing lines
  • Plan the location, movement path, and later paralleling expansion method for mobile or containerized generator sets
  • confirm temporary distribution, low voltage cabinets, output circuit breakers, cable paths and critical load zoning in advance
  • Confirm whether there is any conflict with the entry and exit of daily fuel tanks, large fuel tanks, refueling channels and construction vehicles

Recommended equipment scope

  • Mobile or container-type diesel generator sets, leaving a reasonable margin according to the stage load
  • Temporary distribution system during construction to differentiate between campsites, construction equipment, drainage, lighting and maintenance loads
  • Reserve parallel control, distribution capacity and cable interfaces for trial production and phased expansion
  • Daily fuel tanks, large fuel tanks and refueling plans to avoid fuel supply becoming a construction stoppage
  • Commissioning and handover checklist, operational duty requirements and basic spare parts to reduce temporary on-site coordination

Engineer assistance

Contact an engineer first, then review the equipment and service scope together

Should construction-stage power serve only the current phase, or reserve interfaces for trial production and later expansion?

Equipment and module scope

Mobile or containerized diesel generator sets, temporary low-voltage distribution, large fuel tanks, output protection, generator paralleling system reservation and phased delivery information.

Information engineers will help organize

  • Construction phases and production schedule
  • Camps, drilling rigs, welding machines, pumping stations and temporary production line loads
  • Generator-set placement, roads, lifting, and refueling paths
  • Follow-up trial production or expansion plan

Related equipment and service

Mobile/container unitTemporary distribution cabinetLarge capacity fuel tankParallel reserved interfaceSpare parts package during construction period

Engineer contact

Contact an engineer to review the right configuration.

If the information is incomplete, contact an engineer first. Start with the mine location, the site problem or the general equipment condition; the engineer will organize the loads, site conditions and configuration scope with you.

Scan WhatsApp to contact an engineer

An engineer will contact you soon to review your site issue and needs.

Scan WhatsApp to contact an engineer WhatsApp: +86 176 8575 2779
Email an engineerfeyqiao@hohank.com
or leave your contact information

An engineer will contact you soon to review your site issue and needs.

High-voltage mine buses and long-distance distribution

For 6.3kV or 10.5kV buses, long cable runs or large unit capacities, a high-voltage generator system reduces current and line losses while integrating switchgear, grounding and paralleling.